City of Evanston
Home MenuWater Storage Reservoir Replacement
Project Summary:
This project includes replacement of a 5.0 million gallon treated water storage reservoir with a new similar sized facility, a new overflow, a new submersible pumping system, and site piping modifications.
Project Address:
555 Lincoln Street
Evanston, Illinois 60208
Project Manager:
Paul Moyano
For questions, please call 847-448-4311
Cost:
The construction cost is $19,213,700.00. The Illinois Environmental Protection Agency’s Public Water
Supply Loan Program (PWSLP) is providing $20,556,256.00 at an interest rate of 1.84 percent to fund
engineering and construction costs. The PWSLP is funded by both state and federal sources.
Schedule:
Construction to begin: February 2019
Expected Completion Date: Spring 2021
Contractors:
Construction done by: Thieneman Construction, Inc.
Construction Phase Engineering Services done by: CDM Smith
Public Meetings:
N/A
Newsletters / Notifications :
- January 26, 2016
- August 04, 2017
- February 15, 2019
Council Actions:
- January 26, 2015
- January 11, 2016
- January 23, 2017
- July 10, 2017
- September 17, 2018
- November 12, 2018