Davis st parking repair 2017Project Summary:

The City will be contracting pavement repairs to the on-street parking stalls on the south side of Davis Street between Ridge Avenue and Elmwood Avenue. There are three sections of pavement within these blocks as depicted in the image above. Work includes removal of the existing deteriorated pavement and replacement with porous concrete paver blocks. 

Project Address:

 The south side of Davis Street between Ridge Avenue and Elmwood Avenue

Project Manager: 

Dan Manis
For questions, please call 847-448-4311

Current Project Phase:

Complete

Public Meetings:

N/A

Newsletters:

2017 Davis Street On-Street Parking Pavement Repairs Newsletter - April 18, 2017

Council Actions: