Project Summary:
The limits of the project are from Lincoln Street to Central Street and the project will be completed in three stages. The project will be begin the week of June 5 with exploration trench to identify the existing utilities within the project limits, including the intersection of Lincoln Street and Green Bay Road. The scope of work with the anticipated schedule for each stage is as follows:
Stage 1: June 5 - June 12
Water main connection and installation in the intersection of Lincoln St and Green Bay Road
Stage 2: June 12 – July18
Water main installation along Green Bay Road from Lincoln Street to Central Street
Stage 3: July 18 – July 28
New water services, patching, and restoration
Project Locations:
Green Bay Road water main replacement project from Lincoln Street to Central Street.