Project Summary:

The limits of the project are from Lincoln Street to Central Street and the project will be completed in three stages. The project will be begin the week of June 5 with exploration trench to identify the existing utilities within the project limits, including the intersection of Lincoln Street and Green Bay Road. The scope of work with the anticipated schedule for each stage is as follows:

Stage 1:  June 5 - June 12

Water main connection and installation in the intersection of Lincoln St and Green Bay Road

Stage 2: June 12 – July18

Water main installation along Green Bay Road from Lincoln Street to Central Street

Stage 3: July 18 – July 28

New water services, patching, and restoration

Project Locations:

Green Bay Road water main replacement project from Lincoln Street to Central Street.

 
 
 
 
 
 
 
 
 
 
Project Managers: 

Sat Nagar, Senior Project Manager
snagar@cityofevanston.org
(847) 866-2967